Completion Notices are issued by Royal Greenwich to show the date it is considered the property was completed for Council Tax purposes.
A Completion Notice is a document that specifies the 'completion date' for newly built properties. It is the date on which the property becomes a dwelling for Council Tax purposes and is the date it is entered into the Valuation list.
The Completion Notice is issued in accordance with Schedule 4A of the Local Government Finance Act 1988 and Section 17 of the Local Government Finance Act 1992.
Where a domestic property is structurally complete, or where the work remaining can reasonably be expected to be completed within three months, a Completion Notice will be served on the 'owner' of the property. The 'owner' is defined as 'the person entitled to possession'.
Where work on a property is not yet completed, the Completion Notice can be served specifying the final completion day of up to three months from the date of service. This is to allow for the remaining works for completion of the property to be carried out.
What criteria are used to decide a completion notice?
To ensure the accuracy of our Completion Notices, Council Officers visit and review dwellings that are being built or altered. Evidence such as photographs will be obtained to enable us to make the right decision.
The Council will consider a property to have reached a stage of substantial completion when it meets the following criteria:
- The basic structure is complete, for example all external walls and roof in place.
- Internal walls are built (although not necessarily plastered).
- Floors laid (although the screed or top coat of concrete need not have been laid).
Many properties will have reached an advanced level of completion where, for example, ceilings are in place, walls have been plastered and second fixing may have commenced. In these circumstances, the amount of time allowed in the notice for full completion of the property may be quite short.
In order to be considered ready for banding, the following work does not need to have been carried out:
- Internal decoration of the property, including the fitting of internal doors
- Final fitting of bathroom and kitchen units
- Final fitting of electrical fixtures, plug points and switches
- Final connection of water, gas and electricity (although services should be laid on to the site).
The criteria for determining completion for Council Tax purposes are substantially different to that for determining completion for Building Control. Therefore, whether building control certificates have been issued or not is not directly relevant.
It is important to remember that a Completion Notice may be served up to three months in advance of the day on which the Council specifies that a property is complete. Therefore, whilst at the date when the notice is sent, the property may well not be complete, the important date to bear in mind is the date that the Council is specifying as the date of completion.
What if a property is complete but not occupied?
If the property is complete, the Council will serve a Completion Notice on the owner as soon as is reasonably practicable. A Completion Notice cannot be backdated, even if the property has been completed for some time.
New properties, whether newly constructed or created by conversion, which are unoccupied and substantially unfurnished will be subject to a full charge when it is brought onto the Council Tax List.
What if the property becomes occupied?
A new or altered dwelling does not require a Completion Notice once someone starts to live there. The date used to enter onto the Council Tax list will be the date of occupation.
What if I disagree with the Completion Notice?
The regulations specify that if you disagree with a Completion Notice you should appeal within 28 days of the date of service of the notice to the Valuation Tribunal Service. Their contact details:
Valuation Tribunal Service2nd Floor
120 Leman Street
Whitechapel
London E1 8EU
Telephone: 0300 123 2035
Email: vtwhitechapel@valuationtribunal.gov.uk
The appeal must be made in writing, stating the grounds for the appeal and should be accompanied by a copy of the Completion Notice that has been issued to you.
Alongside the above, you can contact us separately to set out the reasons why you disagree with the date of completion and provide additional information to support your case. If we agree, a revised Completion Notice will be issued, if necessary.
Please note that Council Tax is payable whilst any application or appeal is being considered.